Erection of lifting equipment: Before construction, lifting equipment needs to be erected to provide support during installation.
Masonry foundation: the steel structure frame needs a solid foundation, so the foundation construction is needed.
Installation of columns and beams: The main parts of the steel structure frame are columns and beams, which need to be installed on the foundation by lifting equipment.
Installation of skeleton: After the columns and beams are installed, the skeleton part of the frame needs to be installed in place with lifting equipment.
Installation of panels and covering materials: the exterior of the frame needs to be covered, and the covering materials need to be installed after the skeleton is installed.
Decoration: Finally, interior decoration is needed, including water and electricity installation, floor paving, wall coating and ceiling decoration.